Irish Rail Bridge
Project Details
  • Site clearance and demolition of old farm building.
  • Laying foundations for Opti-cadre units and VSL panels.
  • Rock breaking out areas for foundations.
  • Installing opti-cadre units.
  • Installing VSL panels around bridge structure.
  • Backfill and constructing roadway towards bridge structure.
  • Fencing embankments and Irish Rail boundary line.
  • Laying surface dressing and installing N2W4 crash barrier.
  • Crash barrier (N2W4) was installed on both sides of the bridge to NRA standards